Latest news after the flood
Oktober 2025:
WITH PLEASURE we welcome you, dear guests, in our beautiful hotel rooms, with breakfast every morning and on the weekdays also with dinner. Our meeting rooms are in use again.
Electricity, wifi and our own heating are running smoothly.
More than 1 year ago, our hotel has been hit by a heavy flood and our main floor and all basements have been flooded.
It was necessary to clean, remove and build up all interior and the complete technical installation. The re-installation will take a couple of months more.
We will do everything to build our house up again.
All floors have been removed, all technical devices have been removed, and everything is dried now!
In week 47 of the year 2024, we have started the rebuilding works, starting in the basement with the bricklayer´s . Sanitary installations and parts of the future heating system have been finished. Stuff´s showers and toilets and the public toilets have been built.
The new heating system and cooling system are being installed starting in April. In the new part of the building, some concrete works have started and the plasterer´s have startet working. Isolation works have been done and a lot of workers are here at the moment to build evenything up again.
Also we are starting to remove and build up new our restaurant and kitchen with wellness.